Timeline

May 2020

Site Acquisition

Harvest Properties acquired the site in May 2020.

October 2021

Selected by the City of San Mateo for Public Private Partnership

Harvest Properties was selected by the City of San Mateo for Public Private Partnerships to produce more affordable housing.

March 2022

Submission of Pre-Planning Application

Submission of the pre-planning application for the project was completed.

Pre-App Description

Sep, 01, 2022

Neighborhood Meeting

Harvest Properties in collaboration with Alta Housing, and Self-Help for the Elderly presented an overview of the project and received input from the community that will be taken into consideration as the project progresses forward.

Meeting Presentation

September 2022

Community Outreach Begins

The community outreach process begins with the launch of the coUrbanize site where city residents, employees, and stakeholders can add their feedback for the project in the comments section.

Oct, 11, 2022

Planning Commission Study Session

Harvest Properties in collaboration with Alta Housing, and Self-Help for the Elderly went in front of the Planning Commission on October 11th to present the development proposal and received input from the Planning Commission that will be taken into consideration as the project progresses forward.

February 2023

Submission of Major Application

Submission of the major application for the project was completed.

Major App Description